| Incident | Date | Description | Location | Severity | Duration | Outcome |
|---|---|---|---|---|---|---|
| INC-2026-114 | 2026-09-21 | Substation fault, partial outage | Leipzig-Ost | Critical | 3 h 12 min | Restored, root cause: cable joint |
| INC-2026-109 | 2026-09-08 | Water main burst | Dortmund-Hörde | Warning | 6 h 40 min | Section replaced |
| INC-2026-097 | 2026-08-17 | Heavy rain, underpass flooding | Stuttgart | Warning | 9 h | Drainage upgrade planned |
| INC-2026-085 | 2026-07-29 | Telecom backbone outage | Frankfurt | Critical | 47 min | Fibre cut, rerouted |
| INC-2026-071 | 2026-07-03 | Bridge closure after inspection | Lüdenscheid | Warning | ongoing | Replacement construction |
| INC-2026-052 | 2026-05-14 | Unauthorised access, pumping station | Bremen | Attention | 1 h 05 min | Verified, police informed |
Audit trail
| User | Time | Action | Destination system | Status |
|---|---|---|---|---|
| M. Becker | 13:55 | Create maintenance ticket — Bridge B-17 | SAP PM | Delivered |
| S. Wagner | 12:34 | Notify infrastructure operator — Substation 17 | Westnetz OCC | Delivered |